A leading seismic survey vessel operator selected Optimarin’s 334m3/hour OBS ballast water treatment system for one of its research vessels.

Goltens had previously completed two successful retrofits for this owner and was awarded this retrofit as well. The timeline was relatively short with only a 3-month window between project kick-off and completion of the installation.

Scope of work

Having completed hundreds of ballast water retrofits on systems much larger with greater design challenges, Goltens was confident it could meet the deadlines.

The scope was for a turnkey delivery inclusive of:

  • 3D scanning & vessel survey
  • Basic and detailed engineering
  • Class approvals
  • Procurement & Prefabrication
  • Project Management
  • System installation and commissioning
  • Installation supervision

Execution

Goltens completed the 3D scanning on-board in a single day and delivered the baseline concept design to the client 11 days later. Moving quickly to get an agreement on the conceptual design, Goltens design engineers delivered the detailed engineering less than 30 days later.

With roughly a month remaining before the planned start of the installation, Goltens moved quickly to acquire the necessary materials and prefabricate the pipe spools, brackets, valves, and other materials and get them delivered to Norway.

Goltens deployed a supervisor, an electrician, and 3 pipefitters to the vessel and completed the installation from end to end in only 15 days.

Download PDF version Download PDF version

In case you missed it

WinGD ammonia engine powers EXMAR LPG carrier
WinGD ammonia engine powers EXMAR LPG carrier

Swiss marine power company WinGD has become the first engine designer to bring an ammonia-fuelled two-stroke marine engine to market following the delivery and installation of its...

Fouling control technologies are even more important for vessel operators following recent IMO MEPC 83 session
Fouling control technologies are even more important for vessel operators following recent IMO MEPC 83 session

Marine industry pioneers gathered at Nor-Shipping in June, with a focus on the key challenges and opportunities driving the transition to a lower-carbon future. With regulations s...

New ABS notation boosts container ship flexibility
New ABS notation boosts container ship flexibility

ABS enhanced its CLP-V(PARR) lashing notation to include a seasonality factor, which gives additional operational flexibility to container ship operators. Introduced in 2024, the...

vfd